3E Network designs a 6 MW Mikkeli AI data center for Nvidia Vera Rubin as 2026 target nears
3 E Network said Friday that the first phase of its Mikkeli AI data-center project in Finland is being designed around Nvidia's Vera Rubin architecture. That decision matters because high-density AI hardware has to be matched with power distribution, liquid cooling and network design before construction is too advanced to change cheaply.
The project is still small and pre-revenue. 3E's Finnish subsidiary signed a 30-year lease for roughly 10 hectares in December 2025. The city of Mikkeli said in January that a 6 MW first phase was targeted for operation in the second half of 2026 and that nearby high-voltage infrastructure could support expansion to about 50 MW, subject to the grid-connection process. The first-phase building permit became legally binding in April, and the company later said site clearance was complete and earthworks were under way.
Those milestones establish a real development site. They do not make 50 MW an operating asset: 6 MW remains the disclosed first phase, while the larger figure describes expansion potential.
The timing is now more informative than the architecture label. The city's second-half 2026 operating target is already under way, yet Friday's update did not disclose a contracted customer, final energized-power date, phase-one capital cost or a procurement commitment for Rubin systems. With less than four months left in the year, the absence of a dated energization or commissioning update has become commercially relevant rather than a routine development-stage omission. Without those links, an Nvidia-compatible blueprint cannot be converted into revenue or return assumptions.
With a 6 MW first phase and limited commercial disclosure, Mikkeli is an engineering-readiness update rather than a hyperscale operating story. Selecting Rubin reduces the risk that power and cooling systems are obsolete before commissioning. The project still has to show that the 6 MW phase will be energized and occupied on terms that pay for the build. For now, engineering readiness has advanced further than the commercial case.
Sources
- 3 E Network, September 11, 2026: https://www.advfn.com/stock-market/NASDAQ/MASK/stock-news/99292724/3-e-network-unveils-mikkeli-ai-data-center-bluepri
- City of Mikkeli, January 9, 2026: https://mikkeli.fi/en/2026/01/09/aurora-core-technology-oy-advances-plans-for-an-ai-data-center-in-mikkeli-finland/
- City of Mikkeli, April 2, 2026: https://mikkeli.fi/en/2026/04/02/aurora-core-technology-data-centre-project-building-permit-becomes-legally-binding/
- 3 E Network construction update, April 6, 2026: https://rss.globenewswire.com/news-release/2026/04/06/3268367/0/en/3-e-network-announces-progress-update-on-finland-ai-data-centre-project-site-clearance-completed-and-earthworks-underway.html
- Nvidia Vera Rubin architecture: https://nvidianews.nvidia.com/news/vera-rubin-full-production-agentic-ai-factory