BloombergNEF Counts Around $1.8 Trillion Raised as AI Data Centers Face Refinancing Risks
At least $1 trillion of debt comes due within five years. CTOL's 11% test tracks the effective rate on CoreWeave's next newly signed debt.
Charging 2.85 percentage points more on $13.4 billion of fixed rate dollar debt due in 2027 would add $381.9 million in annual interest. The scenario uses October 2026 Treasury yields and assumes unchanged credit spreads. BloombergNEF counts around $1.8 trillion raised between 2020 and the first half of 2026 across debt, equity and securitised instruments. Raising money starts construction; refinancing decides how much future cash goes to creditors.
We would lend selectively to the AI buildout, with CoreWeave's next debt issue as our price check. We expect the largest neocloud borrower to sign new debt at an effective rate of 11% or less, with credit remaining available to chosen developers. Of the money raised, $794 billion came between the third quarter of 2025 and the first half of 2026, or $794 billion over $1.8 trillion equals 44.1%. BloombergNEF estimates that at least $1 trillion of debt comes due within five years. A bank deciding whether to finance a project today is already deciding which developer will reach the repayment dates.
The FINANCING GAP is the risk that contracted demand leaves a borrower without enough operating income to cover interest and its maturity schedule. It is measured against earnings and debt payments, rather than signed customer commitments. The $13.4 billion of fixed rate dollar debt due in 2027 is 1.34% of the $1 trillion minimum, using $13.4 billion divided by $1 trillion. That percentage compares a narrow category with a broader floor. Lenders also determine their own credit spreads, which can turn this conditional 2027 bill into a more expensive refinancing.
The sharpest concentration comes after 2029. BloombergNEF finds neocloud maturing debt rising eighteenfold between 2029 and 2030. Some $49 billion then matures from 2030 through 2032, about 65% of outstanding neocloud borrowing as of September 2026. CoreWeave and Nebius account for 80% of that $49 billion, or $39.2 billion. As Bloomberg reports, most debt coming due by 2030 is also concentrated among eight developers, including Vantage Data Centers, Switch and Databank. Credit officers can focus on a few balance sheets, but one refusal can strand a substantial piece of planned capacity.
The CoreWeave filing for 30 September 2026 turns that abstract risk into cash demands. Current recourse debt of $9.183 billion plus $1.389 billion of current nonrecourse debt gives $10.572 billion, against $4.122 billion of cash, or 2.6 times. Third quarter net interest expense was $846 million on $3.661 billion of revenue, a 23.1% burden before other costs. Cash on hand covers only part of the near term debt bill. For this borrower, access to credit determines whether the next expansion can be funded alongside existing obligations.
Those lenders can also point to substantial customer contracts. CoreWeave had $132.3 billion in remaining performance obligations against $47.5 billion of total indebtedness at September's end, or $132.3 billion divided by $47.5 billion equals 2.79 times. The company expects 36% of those obligations to be recognised by 30 September 2028 and another 38% during the following 24 months. Yet property and equipment purchases reached $23.558 billion in the first nine months of 2026, compared with $5.638 billion of operating cash flow. Customers promise future revenue; equipment vendors require present money. Contracted demand helps the lending case while leaving a financing requirement that keeps growing with construction.
CoreWeave’s lenders have already put very different prices on its debt. CoreWeave's DDTL 1.0 carried a 15% effective rate at 30 September 2026, while DDTL 2.1 and 3.0 stood at 9% and DDTL 5.5 at 11%. These are different facilities, so the six percentage point difference between 15% and 9% is a comparison across instruments. DDTL 4.0 also ties floating borrowing to daily compounded SOFR plus 2.25%. Lenders have charged the same borrower markedly different prices; the next signed facility will show whether the recent 9% to 11% range survives renewed scrutiny.
A lender can end a construction project years before the developer misses a scheduled maturity. Forbes quoted Jeffrey Moerdler on 16 October 2026: "In the next three years we're going to see a bunch of bankruptcies". It found about $4 billion of CoreWeave corporate debt trading below 80 cents on the dollar, and $37 billion of $80 billion in data center bonds raised so far in 2026 rated junk, or 46.3%, against $8.6 billion of junk issuance in 2025. BloombergNEF also warns about construction debt at TeraWulf and Crusoe. The bear's mechanism is simple: a developer loses financing while building, fails to deliver capacity and enters distress before its largest scheduled repayment.
The bonds and the construction cash tell different stories about the same year. In the first nine months of 2026, CoreWeave received $21.346 billion of net cash from financing activities against $23.558 billion of capital spending, supported by $5.638 billion of operating cash flow. At 30 September it also had $5.7 billion of undrawn availability. Money was reaching construction and contracted revenue was scheduled to follow, while several facilities carried effective rates of 9% to 11%. We expect rationing at those prices rather than a uniform lending shutdown. The FINANCING GAP becomes lethal when the next facility is refused or priced beyond what the project can service.
The US telecommunications boom from 1996 to 2002 supplies a frightening example of lenders financing capacity ahead of revenues. The Richmond Fed's account of that collapse tracks competitive local exchange carrier market value from $86.4 billion in 1999 to $32.1 billion in February 2001, then $3.77 billion in February 2002. The declines were 63% and then 88%, as investment gave way to bankruptcy filings. Those operators built without contracted take or pay demand. CoreWeave's $132.3 billion in remaining obligations provides a different revenue foundation, though its $23.558 billion nine month equipment bill still has to be financed. Contracts make projects bankable only when a creditor will advance the cash.
Lender selection also determines which suppliers can count on an order. BloombergNEF's 20 November 2026 account puts Nvidia's customer backstops at up to $118 billion. Its up to $32 billion of neocloud compute commitments take effect only if the providers secure financing. A developer that loses credit can therefore lose access to purchases intended to support its future revenue. The maturity wall is a schedule of dates; the financing decisions that shape the eventual losses happen before those dates arrive.
We would finance selected developers while expecting CoreWeave's next signed debt to cost no more than 11% effective interest, since a higher rate would threaten our selective credit case. We would be wrong if its annual report for 2026, due by 31 March 2027, lists any facility or note signed after 30 September 2026 at an effective rate above 11%.