Australia's Data Centre Lobbying Analysis Counts 119 Meetings as NextDC's M3 Expansion Waits for Power

By
CTOL Staff Reporter
1 min read

The 119 meetings across five jurisdictions over three years, mostly in 2026, contrast with NextDC's delayed M3 power connection. We expect M3 contract revenue to remain excluded from FY27 guidance at the February 2027 half year results.

At West Footscray, Australia's artificial intelligence ambitions ran into a proposed 22 metre power pole. Jemena suspended network works amid community opposition and a lack of council approval, leaving NextDC's M3 expansion waiting for electricity despite signed customer contracts. We would pass on NextDC as a trade on Australia's data centre lobbying disclosure, expecting M3 contract revenue to remain excluded from FY27 guidance at the February 2027 interim results. Ministers can accelerate a policy decision; the distributor still has to build the connection.

Transparency International Australia's November 2026 analysis counted 119 meetings between executives of ten data centre companies and senior politicians across five jurisdictions over three years, mostly in 2026. Only those jurisdictions publish ministerial diaries, so 119 is a count of observable access. It identified at least 93 registered federal lobbyists across ten third party firms, including 40 former ministers, advisers or senior officials. Access Without Power is the gap between securing an audience and obtaining the permits and electricity that let a customer contract generate revenue. The meetings impress a board; the grid has its own timetable.

The lobbying effort also has a price. Donations from major data centre companies and their contracted lobbying firms climbed from A$685,000 to A$1.8m over three years, while federal donations and other receipts totalled A$3.4m over four. NextDC provides a more material figure for project execution. In its 21 October 2026 ASX update, NextDC cut FY27 net revenue guidance from between A$615m and A$640m to between A$475m and A$500m. A$627.5m minus A$487.5m equals A$140m, or 22.3% of the earlier midpoint. Shares closed 41.7% lower at A$5.35 that day. Those were changes to company guidance rather than realised M3 losses, and shareholders absorbed a sharp repricing.

The same announcement cut underlying EBITDA guidance from between A$385m and A$410m to between A$245m and A$265m. A$397.5m minus A$255m is A$142.5m, or 35.8% of the earlier midpoint. M3 was expanding from 60MW towards 225MW of contracted capacity. The permit for stages six and seven had been with Victoria since February 2026, and chief executive Craig Scroggie said on 21 October that February 2027 was the earliest approval he expected after the 28 November 2026 state election. NextDC expected the next grid supply no earlier than mid 2027. NextDC sold space on one timetable while the network followed another.

Queensland offers the best argument for the lobbying effort. Premier David Crisafulli met data centre executives 13 times, including three meetings with NextDC executives in three weeks during August and September 2026; Queensland's fast track data centre framework followed. Sally Mackenzie, president of the Australian Professional Government Relations Association, described such engagement as "the system working as intended". Political access has an economic use when governments can improve approval processes for future projects, even though it provides no automatic remedy in Victoria. Firmus Technologies met Tasmanian ministers ten times in 2026 and continued expanding despite sustained opposition. That is the strongest case for lobbying: policy improvements can keep a pipeline moving even when individual sites face resistance.

NextDC's own November figures give that argument weight on the same FY27 horizon. At its 20 November 2026 AGM, management increased revenue guidance to A$485m to A$500m and underlying EBITDA to A$260m to A$275m. Its forward order book stood near 565MW, with a development pipeline above 5GW and A$1.1bn in convertible notes due in 2031. The forward orders give managers a reason to persevere while M3 waits. A permit followed by workable network changes offers the opposing route to earlier M3 electricity and FY27 contract revenue. The FY27 revenue midpoint had recovered to A$492.5m from October's A$487.5m; the EBITDA midpoint reached A$267.5m from A$255m. Yet the revenue midpoint remained below August's A$627.5m and the update still excluded M3 contracts. Rising guidance offers reassurance in the same financial year that M3 is delayed.

There is money behind the opposite interpretation as well. Goodman Group and Digital Realty acquired a 9.9% interest in NextDC through a jointly owned vehicle from 3 to 6 November 2026, paying an average A$9.22 per share against the A$5.35 close on 21 October. Their stake covered a business much broader than the delayed M3 expansion. Their purchase illustrates that an infrastructure operator can regain investor support before a troubled connection is repaired; it says less about the timing of M3 revenue. Their A$9.22 entry offers a historical equity price, rather than an electricity delivery date.

Ireland supplies the uncomfortable comparison. On 23 November 2021 its regulator introduced criteria for assessing data centre grid connections by location, onsite generation and flexibility. Data centres' share of national electricity demand had climbed from 5% in 2015 to 22% in 2024. The regulator established a conditional connection pathway on 12 December 2025, including generation or storage matching maximum import capacity and at least 80% of annual demand from additional Irish renewables, with a six year transition. A national regulator's rule differs from a Victorian pole approval, but the roughly four year interval shows how long grid conditions can dictate timing.

Singapore shows the other outcome, with an important limit. After a pause beginning in 2019, authorities opened a pilot in 2022 aimed at about 60MW. On 14 July 2023, they provisionally awarded about 80MW to four operators from more than 20 proposals. Scarce capacity did return to the allocation process. Singapore was selecting applicants centrally, rather than dealing with a distributor's local construction route, and a provisional award is a step before physical delivery. Its reopening illustrates a route to success, with years of waiting attached.

New South Wales offers a domestic policy victory of a narrower kind. Its parliamentary inquiry tabled 26 recommendations on 5 November 2026 after 143 submissions and five hearings, stopping short of a moratorium in a state with more than 90 operating data centres. It favoured a strategy and cumulative impact assessment. Yet Goodman's Mars proposal in Lane Cove and another proposal in Hazelmere, Western Australia, were withdrawn after community opposition. A permissive recommendation keeps applications alive without securing a viable connection.

Federal expectations for large data centres appeared on 23 March 2026, followed by a September consultation on energy, water and community engagement. Those proposals address conditions for expansion while NextDC still needs a Victorian permit and network works. Access Without Power is visible in that mismatch: an approvals framework can improve while contracted capacity remains stranded. A permit for M3 stages six and seven and resumed Jemena works would matter more than another ministerial meeting; the consequential financial indicator is NextDC's guidance treatment of M3 contracts.

We would pass on NextDC as a lobbying led trade, expecting M3 contract revenue to remain excluded from FY27 guidance at the February 2027 half year results. We would be wrong if NextDC's February 2027 ASX interim results expressly reinstated M3 contract revenue in FY27 guidance following resolution of the grid constraint.

You May Also Like

This article is submitted by our user under the News Submission Rules and Guidelines. The cover photo is computer generated art for illustrative purposes only; not indicative of factual content. If you believe this article infringes upon copyright rights, please do not hesitate to report it by sending an email to us. Your vigilance and cooperation are invaluable in helping us maintain a respectful and legally compliant community.

Subscribe to our Newsletter

Get the latest in enterprise business and tech with exclusive peeks at our new offerings

We use cookies on our website to enable certain functions, to provide more relevant information to you and to optimize your experience on our website. Further information can be found in our Privacy Policy and our Terms of Service . Mandatory information can be found in the legal notice