The $300 Million Sale Puts an $18 Billion AI Campus Loan on a Different Price Curve

By
CTOL Staff Reporter
1 min read

The same New Mexico financing slipped from September quotes to a reported sale in the mid-80s, while other Oracle-linked sites still trade on better indications.

On 18 September 2026, banks privately quoted loans on New Mexico's Project Jupiter at 89 to 91 cents on the dollar. Weeks later, HSBC reportedly sold roughly $300 million of that $18 billion financing in the mid-80s. Bloomberg described the sale on 16 November 2026, after Oracle had issued a force majeure notice to the developer. We would pass at a scenario price of 85 cents. A bank exiting before the campus opens has put a price on the cost of waiting.

Oracle's Wisconsin and Texas projects carry loans that were quoted above 90 cents on 17 November 2026. Site Spread is the price difference between Oracle-linked project debt at different campuses, tested against each project's construction schedule and payment rights. You own exposure to different building risks under the same tenant credit. We expect ING's New Mexico slice to clear below 90 cents because of its delivery risks, rather than any run on OpenAI credit.

A patient lender has a persuasive 2028 demand case. Oracle reported $664 billion in companywide remaining performance obligations on 10 September 2026, up $209 billion year over year. Jupiter's financing had a private investment-grade rating; Oracle says the project remains on its planned schedule and that it is fully committed to New Mexico, while Blue Owl says the notice does not change its financial commitments. At its planned 2028 opening, a 2.45 GW campus serving a committed tenant would turn construction lending into a claim on an operating asset.

Oracle's force majeure notice would allow payment delays if the facility misses its 2028 target, according to Bloomberg's sources as reported by TechCrunch. On 18 September 2026, SynMax said the initial phase was at least seven months behind its proposed opening. The gas pipeline was delayed to 1 February 2027, and the air permit faces a decision deadline of 23 November 2026. The lender's 2028 income case faces a contractual delay mechanism, while construction capital bears the wait.

The 89 to 91 cent indications on 18 September 2026 and the later Bloomberg account concern the same $18 billion Jupiter financing. At an illustrative 85 cents for the reported mid-80s sale, the move from those indications is four to six points, calculated as 89 to 91 minus 85. The first prices were private quotes; the second is a sale reported by people familiar with it, rather than a published trade confirmation. The reported exit price has fallen before construction is complete.

For HSBC's roughly $300 million slice, an 85-cent scenario implies a $45 million discount to par ($300 million × 0.15), without claiming that 85 cents was its exact execution price. On ING's separate $25 million New Mexico slice, the same scenario would yield $21.25 million ($25 million × 0.85), leaving $3.75 million under par ($25 million × 0.15). A few cents on project loans transfer millions of dollars from the bank that wants out to the investor willing to wait.

The Financial Times quoted an unnamed source on 17 November 2026 calling Societe Generale's disposal "a portfolio management exercise rather than acute concerns over credit quality." Financing construction absorbs balance-sheet capacity, and a bank can sell healthy loans to make room for other assets. Societe Generale's $300 million of Wisconsin and Texas project debt was quoted above 90 cents; those are quotes, not confirmed sales. Portfolio management explains selling; HSBC's reported mid-80s Jupiter transaction leaves the site price question open.

Oracle's corporate credit rating stood one notch above junk in September 2026, and banks were holding more Oracle-linked project debt than planned. That pressure affects the tenant across sites. On 17 November 2026, Wisconsin and Texas were quoted above 90, while Bloomberg's 16 November account placed the earlier New Mexico sale in the mid-80s. Jupiter has different building tranches, while comparative seniority and terms remain undisclosed. Site Spread singles out a geographic pricing gap; it leaves room for loan structure alongside delivery risk. That unknown belongs in the price of a particular tranche.

The talk of European banks abandoning OpenAI stretches a $25 million connection into an $800 million story. ING put $500 million of debt on auction, so its New Mexico slice is 5% ($25 million / $500 million), and 3.1% of the combined ING and Societe Generale offerings ($25 million / $800 million). ING's auction was described on 5 November 2026, before California sued OpenAI on 16 November. OpenAI's own financing statement of 31 March 2026 says its roughly $4.7 billion bank revolver was undrawn at close. The Jupiter loans finance an Oracle-leased project, so the immediate mark belongs to construction lenders, not to OpenAI's revolver.

The California complaint filed on 16 November 2026 concerns how OpenAI tests autonomous agents. The attorney general cites at least 80 incidents, and the complaint seeks $2,500 per proved violation plus disgorgement and abatement. Treating 80 incidents as 80 violations gives a $200,000 scenario (80 × $2,500); the legal count remains undecided. The Wall Street Journal's third-quarter figures, relayed by Reuters, put OpenAI's operating loss at $10.9 billion. The penalty illustration is economically slight; restrictions on the testing operation would be the more consequential claim.

OpenAI spokesman Drew Pusateri told NBC on 16 November 2026, "This lawsuit appears to single out OpenAI over a challenge that's been identified by every major AI lab". The company's 26 August 2026 account says the incident left customer data, product functionality and availability unaffected. OpenAI also says it is creating more isolated sandboxes and restricting internet access. Yet the state's 80-incident allegation focuses on the controls inside testing, not a tally of lost customers. You would be pricing possible changes to how experiments run, rather than compensation for a quantified consumer loss.

In 2021, Oklahoma's Supreme Court reversed a $465 million public-nuisance award against Johnson & Johnson, partly because manufacturers typically lose control after a product is sold. California alleges conduct inside OpenAI's own test environment, where that distinction breaks. On 26 August 2026, the California attorney general announced a proposed Meta settlement of up to $17 billion over ten years, including a default two-hour daily limit for under-18s, an independent auditor and $1.5 billion to $2.1 billion for California if approved. That was a multistate consumer case, rather than this single-state testing dispute. That settlement's terms concern platform behavior; the Jupiter debt discount concerns delayed physical capacity.

ING's bids are due 19 November 2026.

We would pass on ING's New Mexico debt at a scenario price of 85 cents because its payment timetable depends on delivery and its tranche protections remain undisclosed. A public sale report by the end of November 2026 showing ING's $25 million New Mexico slice cleared at 90 cents or above would prove that our expected sub-90 clearing price is wrong. Until then, you are buying an unfinished campus whose tenant has a contractual way to delay payment if completion slips.

You May Also Like

This article is submitted by our user under the News Submission Rules and Guidelines. The cover photo is computer generated art for illustrative purposes only; not indicative of factual content. If you believe this article infringes upon copyright rights, please do not hesitate to report it by sending an email to us. Your vigilance and cooperation are invaluable in helping us maintain a respectful and legally compliant community.

Subscribe to our Newsletter

Get the latest in enterprise business and tech with exclusive peeks at our new offerings

We use cookies on our website to enable certain functions, to provide more relevant information to you and to optimize your experience on our website. Further information can be found in our Privacy Policy and our Terms of Service . Mandatory information can be found in the legal notice